Get the test CCM certification is not achieved overnight, we need to invest a lot of time and energy to review, and the review process is less a week or two, more than a month or two, or even half a year, so CCM exam questions are one of the biggest advantage is that it is the most effective tools for saving time for users. Users do not need to spend too much time on CCM questions torrent, only need to use their time pieces for efficient learning, the cost is about 20 to 30 hours, users can easily master the test key and difficulties of questions and answers of CCM Prep Guide, and in such a short time acquisition of accurate examination skills, better answer out of step, so as to realize high pass the qualification test, has obtained the corresponding qualification certificate.
Many of the candidates like the Soft version of our CCM exam questions. The software of CCM guide torrent boosts varied self-learning and self-assessment functions to check the results of the learning. The software can help the learners find the weak links and deal with them. Our CCM Exam Questions boost timing function and the function to stimulate the exam. Our product sets the timer to stimulate the exam to adjust the speed and keep alert. So it is worthy for you to buy our CCM exam questions.
For customers who are bearing pressure of work or suffering from career crisis, Certified Case Manager Certification Exam (CCM) learn tool of inferior quality will be detrimental to their life, render stagnancy or even cause loss of salary. So choosing appropriate CCM test guide is important for you to pass the exam. One thing we are sure, that is our CCM Certification material is reliable. With our high-accuracy CCM test guide, our candidates can grasp the key points, and become sophisticated with the exam content. You only need to spend 20-30 hours practicing with our Certified Case Manager Certification Exam (CCM) learn tool, passing the exam would be a piece of cake.
NEW QUESTION # 26
Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).
Answer: A,D
Explanation:
Dayworksrefer to works executed on a time basis (e.g., labor and plant) with payment made according to predetermined rates rather than a lump sum or unit rate contract price.
* Option Aisincorrect. Even if a Daywork Schedule is not initially included, the dayworks Sub-Clause (e.g., Sub-Clause 13.7 in Red and Yellow Books, 13.8 in Silver Book 1999) still applies to dayworks ordered during the contract execution. The schedule facilitates pricing, but the Sub-Clause governs the method and conditions for dayworks.
* Option Biscorrect. The dayworks Sub-Clause is applicable not only to traditional construction works but can also be applied to other types of works, such as variations or additional works that cannot be precisely measured or foreseen and are charged on a time basis.
* Option Cisincorrect. The dayworks Sub-Clause is used in all FIDIC standard forms (Red, Yellow, and Silver Books), not only for remeasurement in the Red Book. In the Yellow Book (plant and design- build) and Silver Book (EPC/turnkey), dayworks are similarly applicable for certain variations or unforeseen works.
* Option Discorrect. The Engineer (in Red and Yellow Books) or the Employer (in the Silver Book, where the Engineer's role is limited) may instruct that a variation be executed on a daywork basis. This instruction is typically used when the scope or quantity cannot be reasonably pre-determined.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 13.7 - Dayworks
FIDIC Yellow Book 2017 Edition, Sub-Clause 13.7 - Dayworks
FIDIC Silver Book 1999 Edition, Sub-Clause 13.8 - Dayworks
FIDIC Contract Manager Study Guide, Module on Contract Administration Procedures
NEW QUESTION # 27
Which one of the following statements is correct regarding the Employer's Representative under the FIDIC Silver Book (edition 1999)?
Answer: C
Explanation:
Comprehensive and Detailed Explanation:
Under the FIDIC Silver Book (1999 edition), the Employer may appoint an Employer's Representative to act on their behalf, but this is discretionary and not mandatory (Option B). The Employer's Representative acts within the authority delegated by the Employer but cannot amend the Contract unless expressly authorized.
Option A is partly correct but less complete than B.
Option C is incorrect; the appointment is not compulsory.
Option D is incorrect; the Employer is not contractually obliged to consult the Contractor for appointment approval.
References:
FIDIC Silver Book 1999 Edition, Clause 1.1 and Clause 3 - Employer's Representative FIDIC Contract Manager Study Guide, Module on Contract Administration
NEW QUESTION # 28
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition
2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
Answer: C
Explanation:
According to the FIDIC Yellow Book 2017, the Commencement Date is the date notified by the Engineer as the date on which the Contractor shall start the execution of the Works (Sub-Clause 8.1). In this case, although the Engineer notified 15 July 2022 as the Commencement Date, it was subject to the issuance of the construction permit. Since the construction permit was only obtained on 1 August 2022, work could not legally commence before that date.
FIDIC recognizes that the Contractor cannot be expected to start before all necessary permissions are granted.
Hence, the effective Commencement Date must be the earliest date on which the Contractor can legally commence work, i.e., the date when the permit was issued (1 August 2022). The contract's requirement that the Commencement Date notification occur no later than 14 days after signing is subject to actual readiness conditions (permit availability).
Therefore, for purposes of delay and completion, the Commencement Date is 1 August 2022. This affects the calculation of the Time for Completion and any delay claims accordingly.
References:
FIDIC Yellow Book 2017 Edition, Sub-Clause 8.1 - Commencement of Works
FIDIC Yellow Book 2017 Edition, Sub-Clause 2.1 - Right of Access to Site and Permits FIDIC Contract Manager Study Guide, Module on Contract Formation and Execution
NEW QUESTION # 29
Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?
(Choose all correct answers - multiple possibilities)
Answer: A,D
Explanation:
Under the FIDIC Red Book and Yellow Book, 1999 editions, the Engineer issues Interim Payment Certificates certifying the amounts due to the Contractor for completed works and materials on site (Sub- Clause 14.6). The Employer is generally bound by the Payment Certificate and must pay accordingly, except where there is a lawful set-off or compensation claim against the Contractor.
Option A is correct because the Employer must pay the amount certified except for compensation claims that may be offset against the payment (Sub-Clause 14.6).
Option D is also correct: If the Employer intends to claim against the Contractor (e.g., for damages or defects), it must notify the Contractor under Sub-Clause 2.5 and provide particulars. The Engineer then assesses and decides on the claim and incorporates any agreed deductions into the Payment Certificate.
Option B is incorrect because the Employer is indeed bound by the Payment Certificate unless lawful deductions or disputes arise.
Option C is incorrect as the Employer can withhold amounts due for compensation claims once these are properly notified and substantiated.
References:
FIDIC Red and Yellow Books, 1999 Edition, Sub-Clause 14.6 - Interim Payments FIDIC Red and Yellow Books, 1999 Edition, Sub-Clause 2.5 - Employer's Claims FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 30
Which one statement regarding the adjustment of the Contract Price as mentioned in Sub-Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?
Answer: B
Explanation:
Sub-Clause 13.8 of the FIDIC Silver Book (1999) allows the Particular Conditions to specify a formula or indices for adjusting the Contract Price for rises and falls in labour and Goods costs. The method set forth may not fully compensate for actual cost changes - it can be lower than the real fluctuations - reflecting practical and commercial considerations.
Option B is correct because the contract permits this flexibility.
Option A is incorrect; full compensation is not guaranteed.
Option C is incorrect; the adjustment can cover materials and labour but may extend beyond.
Option D is incorrect; adjustments can be calculated from different dates as specified.
References:
FIDIC Silver Book 1999 Edition, Sub-Clause 13.8 - Adjustments for Changes in Cost FIDIC Contract Manager Study Guide, Module on Payment Adjustments
NEW QUESTION # 31
......
With the arrival of the flood of the information age of the 21st century, people are constantly improve their knowledge to adapt to the times. But this is still not enough. In the IT industry, Medical Professional's CCM exam certification is the essential certification of the IT industry. Because this exam is difficult, through it, you may be subject to international recognition and acceptance, and you will have a bright future and holding high pay attention. FreeDumps has the world's most reliable IT certification training materials, and with it you can achieve your wonderful plans. We guarantee you 100% certified. Candidates who participate in the Medical Professional CCM Certification Exam, what are you still hesitant?Just do it quickly!
CCM Practice Test Fee: https://www.freedumps.top/CCM-real-exam.html
Besides, there are Medical Professional CCM free pdf demo questions for you to download and you are allowed to free update for one year after purchase, Our IT elites design the best CCM practice exam by collecting the complex questions and analyzing the key points of the actual test over years, All workers will take part in regular training to learn our CCMstudy materials, So our CCM study guide can be your best choice.
We will also briefly cover how to install additional Exchange servers once CCM your primary server is in place, I think the commercial world is significantly ahead of the government when it comes to applied software security.
Besides, there are Medical Professional CCM free pdf demo questions for you to download and you are allowed to free update for one year after purchase, Our IT elites design the best CCM practice exam by collecting the complex questions and analyzing the key points of the actual test over years.
All workers will take part in regular training to learn our CCMstudy materials, So our CCM study guide can be your best choice, And pass the Medical Professional CCM exam is not easy.